  • PLANNED SHUTDOWN FOR THE MONTH OF – DECEMBER 2022

 

Date of Shutdown TIME Name of Substation/ Line/ Feeder Purpose of Shutdown Approx Load to be Affected
FROM TO
01/12/2022  9:00 AM 11:00 AM Singjamei feeder HT poles shifting  2 MW
02/12/2022  9:00 AM 4:00 PM Wangjing Feeder Erection, Highway Expansion  1.5 MW
03/12/2022  9:00 AM 4:00 PM 11kV Western & JNV Feeder HT poles shifting  2.5 MW
03/12/2022  8:00 AM 4:00 PM Reangpang-Tamenglong line Shifting of wooden 33kv SP  2 MW