(As per the Data Furnished by STATE LOAD DISPATCH CENTRE, SLDC, MANIPUR)
- PLANNED SHUTDOWN FOR THE MONTH OF – MARCH 2022
Date of Shutdown | TIME | Name of Substation/ Line/ Feeder | Purpose of Shutdown | Approx Load to be Affected | |
FROM | TO | ||||
19/03/2022 | 9:00 AM | 4:00 PM | Multi Ckt 2 | Rectification of Multi Ckt 1 | 0 MW |
26/03/2022 | 9:00 AM | 5:00 PM | From Reangpang to Tamenglong HQ | Shifting and Re-Stringing of 33KV HT Line | 2 MW |
27/03/2022 | 11:00 AM | 3:00 PM | STPI | Jungle cutting and line maintenance | 3.5 MW |
30/03/2022 | 11:00 AM | 3:00 PM | Mantripukhri feeder-2 | Jungle cutting and line maintenance | 3.5 MW |
30/03/2022 | 7:30 PM | 11:30 AM | 11KV Kakwa | Jungle cutting | 2 MW |