A) Transmission system (Under State Plan):
- Construction of 2×12.5 MVA 132 KV Substation along with associated 132 KV line & related works at Tipaimukh
Status
Sub-Station
- Foundation of Transformer, Gantry and Major Equipment completed
- Control Room Building is 95% Completed
Line
- Tower Erection is 50% completed.
- Stringing is yet to start.
Target to be completed: December, 2017
- Construction of 132 kV link transmission line for evacuation of power from 400/132 kV sub-station at Thoubal to 132 kV substations at Moreh
Status
- Work is in progress
Target to be completed: March, 2018
- Installation of 2×2.5MVA, 33/11 KV Sub-station at Kasom-Khullen with associated line
Status
Sub-Station
- Work Completed except Control room finishing, cable laying and termination
Line
- Pole Erection – 38 Km out of 41 Km completed
- Stringing – 36 Km out of 41 Km completed
Target to be completed: June, 2017
- Construction of 132 kV link transmission line for evacuation of power from 400/132 kV sub-station at Thoubal to 132 kV substations at Kongba, Yaingangpokpi and Hundung
Status
- Tower Foundation – 43 out of 44 nos completed
- Tower Erection – 34 out of 44 nos completed
- Stringing – 4.5 Km out of 11 Km completed
Target to be completed: June, 2017
- Construction of 33 kV D/C line on steel tubular poles from 132/33 kV sub-station, Thoubal to 33/11 kV sub-station at Thoubal (old)
Status
- Pole Erection is completed.
- Stringing – 5 Km out of 6 Km
Target to be completed: June, 2017
- Installation of 2×2.5 MVA 33KV S/S at Paoyi
Status
Work is in progress
Target to be completed: May, 2018
- Installation of 2×2.5 MVA 33KV S/S at Thuyeng
Status
Work is in progress
Target to be completed: May, 2018
- Installation of 2×2.5 MVA 33KV S/S at Gumnom
Status
Work is in progress
Target to be completed: May, 2018
- Upgradation of 33/11 kV Sub-Station at Khoupum by installing 2×2.5 MVA Transformer
Status
Work in progress- 20% completed
Target to be completed: February, 2018
- Installation of 2 nos. of 400kV Line bays at Imphal (PG) Sub-Station.
Status
15% of the work completed.
Target to be completed: March, 2018
- Installation of 132 kV S/C Line (2ndCkt) on D/C towers from Leimatak PH (NHPC) to 132 kV S/S at Ningthoukhong.
Status
35% of the work completed.
Target to be completed: November, 2017
- Construction of 132 kV S/C Line (3rdCkt) on D/C towers from 132 kV Yurembam S/S (State) to 132 kV Yurembam S/S (PGCIL)
Status
35% of the work completed.
Target to be completed: November, 2017
B) Transmission system (Under NLCPR funding & State Plan support)
- Construction of 3×105 MVA 400/132 KV Sub-Station at Thoubal
Status
- Completed and equipment testing in progress
Target to be completed: April, 2018
- Construction of 400KV line on D/C towers initially charged at 132 KV from Yurembam To Thoubal via Nambol
Status
- Tower Foundation – 116 towers completed out of 137.
- Tower Erection – 106 towers completed out of 137.
- Stringing – 20 Km out of 45.1 Km
Target to be completed: February, 2018
- Installation of 2×12.5 MVA, 132/33 KV S/S along with the associated 132 KV line & related civil works at Thanlon, Churachandpur District.
Status
Sub-Station
- Foundation of Transformer, Gantry and Major Equipment completed
- Control Room Building Completed
- 90% of the erection of major equipment completed.
Line
- Tower Foundation – 234 towers completed out of 242.
- Tower Erection – 224 towers completed out of 242.
- Stringing – 52.7 Km out of 66 Km
Target to be completed: September, 2017
- Installation of 2X12.5 MVA,132/33 KV Sub-station at Moreh with associated 132 KV line and related civil work on turn key basis under NLCPR
Status
Sub-Station
- Foundation of Transformer, Gantry and Major Equipment completed
- Control Room Building Completed
- Erection of major equipment is in progress.
Line
- Tower Foundation – 158 towers completed out of 181.
- Tower Erection – 70 towers completed out of 181.
- Stringing – 3 Km out of 45 Km
Target to be completed: September, 2017
- Installation of 2×5 MVA, 33/11 KV S/S along with the associated 33 KV line & related civil works at Nungbi Khullen, Ukhrul District.
Status
Sub-Station
- Foundation of Transformer, Gantry and Major Equipment completed
- Erection of gantry tower completed
- Control Room Building Completed
- Erection of major equipment is in progress.
Line
- Pole Erection – Completed
- Stringing – 42 Km out of 45 Km
Target to be completed: June, 2017
C) Transmission system (Under NEC funding & State Plan Support)
- Stringing of 132 KV S/C line Second Circuit on D/C Tower from Kakching to Churachandpur, Manipur
Status
- Work almost completed except two spans of 700 m due to forest clearance.
Target to be completed: will be completed as soon as after getting forest clearance.
- Installation of 2×5 MVA, 33/11 KV Sub-station at Mao with associated line
Status
Sub-Station
- Erection of Equipment completed
- Control Room Building Completed
- Transformer Erection, panel erection in progress
Line
- Survey Completed
- Tower Erection – For 0.5 km out of 5.5 kms Completed
Target to be completed: June, 2017
- Installation of 2×5 MVA, 33/11 KV Sub-station at Mayangkhang with associated line
Status
Sub-Station
- Land Development
- Foundation of Transformer, Major Equipment completed
- Control Room Building – brick work Completed
- Material and equipment supplied – 90%
Target to be completed: August, 2017
D) Transmission system (Under IPDS funding)
- Installation of 1×3.15 MVA 33KV S/S at Wangjing Moirangpalli
Status
- Land Development is completed
- Gantry and Equipment foundation is in progress.
- Control room building- 60% completed
- Material and equipment supplied – 70%
Target to be completed: May, 2018
- Installation of 2×5 MVA 33KV S/S at Yairipok
Sub-Station
- Land Development is completed
- Transformer Foundation is completed
- Gantry and Equipment foundation is 90% completed.
- Control Room is completed.
- Material and equipment supplied – 70%
Target to be completed: May, 2018
- Installation of 2×5 MVA 33KV S/S at Heirok
Sub-Station
- Land Development is completed
- Transformer Foundation is completed
- Gantry and Equipment foundation is 90% completed.
- Control Room is completed.
- Material and equipment supplied – 70%
Target to be completed: May, 2018
- Installation of 2×5 MVA 33KV S/S at Wangoi
Sub-Station
- Site has been identified and land development to start shortly.
- Material and equipment supplied – 50%
Target to be completed: May, 2018
- Augmentation of 33/11 kV S/S from 1×3.15 MVA to 2×3.15 MVA at Kangpokpi
Sub-Station
- Material and equipment supplied – 50%
Target to be completed: May, 2018
- Augmentation of 33/11 kV S/S from 1×5 MVA to 2×5 MVA at Karong
Sub-Station
- Material and equipment supplied – 50%
Target to be completed: May, 2018