Latest News

  • Final Seniority List of Deputy Manager(Fin. & Accts.) Read more...
  • Tentative seniority list of WCCA Read more...
  • PROHIBITION OF SEXUAL HARASSMENT OF WOMEN AT THE WORK PLACE Read more...
  • Final Seniority List in respect of Manager(HR), DM(Elec/Civil/IT) & Computer Operator. Read more...
  • Tentative Seniority List: Manager(HR), Deputy Manager(Elect), Deputy Manager(Civil), Deputy Manager(IT) & Computer Operator, MSPCL Read more...

Projects

Click here to download- Vision 2030 ( in respect of MSPCL)



Sl. No.ParticularsTotal Capacity (as on January, 2016)Total Capacity (as on March, 2017)Achievement during 2016-17
1132/33 KV transformation capacity517 MVA597 MVA80 MVA
2132 KV transmission lines537.1 Kms573.1Kms36 Kms
333/11 KV transformation capacity508.2 MVA559.65 MVA51.45 MVA
433 KV Sub-transmission lines1318.73 Kms1462.23 Kms143.5 Kms

A) Transmission system (Under State Plan):

  1. Construction of 2×12.5 MVA 132 KV Substation along with associated 132 KV line & related works at Tipaimukh

Status 

Sub-Station

  1. Foundation of Transformer, Gantry and Major Equipment completed
  2. Control Room Building is 95% Completed

Line

  1. Tower Erection is 50% completed.
  2. Stringing is yet to start.

Target to be completed: December, 2017 

  1. Construction of 132 kV link transmission line for evacuation of power from 400/132 kV sub-station at Thoubal to 132 kV substations at Moreh

Status 

  1. Work is in progress

Target to be completed: March, 2018

  1. Installation of 2×2.5MVA, 33/11 KV Sub-station at Kasom-Khullen with associated line

Status 

Sub-Station

  1. Work Completed except Control room finishing, cable laying and termination

Line

  1. Pole Erection – 38 Km out of 41 Km completed
  2. Stringing – 36 Km out of 41 Km completed

Target to be completed: June, 2017

  1. Construction of 132 kV link transmission line for evacuation of power from 400/132 kV sub-station at Thoubal to 132 kV substations at Kongba, Yaingangpokpi and Hundung

Status 

  1. Tower Foundation – 43 out of 44 nos completed
  2. Tower Erection – 34 out of 44 nos completed
  3. Stringing – 4.5 Km out of 11 Km completed

Target to be completed: June, 2017

  1. Construction of 33 kV D/C line on steel tubular poles from 132/33 kV sub-station, Thoubal to 33/11 kV sub-station at Thoubal (old)

Status 

  1. Pole Erection is completed.
  2. Stringing – 5 Km out of 6 Km

Target to be completed: June, 2017

  1. Installation of 2×2.5 MVA 33KV S/S at Paoyi

Status 

Work is in progress

Target to be completed: May, 2018

  1. Installation of 2×2.5 MVA 33KV S/S at Thuyeng

Status 

Work is in progress

Target to be completed: May, 2018

  1. Installation of 2×2.5 MVA 33KV S/S at Gumnom

Status 

Work is in progress

Target to be completed: May, 2018

  1. Upgradation of 33/11 kV Sub-Station at Khoupum by installing 2×2.5 MVA Transformer

Status 

Work in progress- 20% completed

Target to be completed: February, 2018

  1. Installation of 2 nos. of 400kV Line bays at Imphal (PG) Sub-Station.

Status 

15% of the work completed.

Target to be completed: March, 2018

  1. Installation of 132 kV S/C Line (2ndCkt) on D/C towers from Leimatak PH (NHPC) to 132 kV S/S at Ningthoukhong.

Status 

35% of the work completed.

Target to be completed: November, 2017

  1. Construction of 132 kV S/C Line (3rdCkt) on D/C towers from 132 kV Yurembam S/S (State) to 132 kV Yurembam S/S (PGCIL)

Status 

35% of the work completed.

Target to be completed: November, 2017

B) Transmission system (Under NLCPR funding & State Plan support)

  1. Construction of 3×105 MVA 400/132 KV Sub-Station at Thoubal

Status 

  1. Completed and equipment testing in progress

Target to be completed: April, 2018

  1. Construction of 400KV line on D/C towers initially charged at 132 KV from Yurembam To Thoubal via Nambol

Status 

  1. Tower Foundation – 116 towers completed out of 137.
  2. Tower Erection – 106 towers completed out of 137.
  3. Stringing – 20 Km out of 45.1 Km

Target to be completed: February, 2018

  1. Installation of 2×12.5 MVA, 132/33 KV S/S along with the associated 132 KV line & related civil works at Thanlon, Churachandpur District.

Status 

Sub-Station

  1. Foundation of Transformer, Gantry and Major Equipment completed
  2. Control Room Building Completed
  3. 90% of the erection of major equipment completed.

Line

  1. Tower Foundation – 234 towers completed out of 242.
  2. Tower Erection – 224 towers completed out of 242.
  3. Stringing – 52.7 Km out of 66 Km

Target to be completed: September, 2017

  1. Installation of 2X12.5 MVA,132/33 KV Sub-station at Moreh with associated 132 KV line and related civil work on turn key basis under NLCPR

Status 

Sub-Station

  1. Foundation of Transformer, Gantry and Major Equipment completed
  2. Control Room Building Completed
  3. Erection of major equipment is in progress.

Line

  1. Tower Foundation – 158 towers completed out of 181.
  2. Tower Erection – 70 towers completed out of 181.
  3. Stringing – 3 Km out of 45 Km

Target to be completed: September, 2017

  1. Installation of 2×5 MVA, 33/11 KV S/S along with the associated 33 KV line & related civil works at Nungbi Khullen, Ukhrul District.

Status 

Sub-Station

  1. Foundation of Transformer, Gantry and Major Equipment completed
  2. Erection of gantry tower completed
  3. Control Room Building Completed
  4. Erection of major equipment is in progress.

Line

  1. Pole Erection – Completed
  2. Stringing – 42 Km out of 45 Km

Target to be completed: June, 2017

C) Transmission system (Under NEC funding & State Plan Support)

  1. Stringing of 132 KV S/C line Second Circuit on D/C Tower from Kakching to Churachandpur, Manipur

Status 

  1. Work almost completed except two spans of 700 m due to forest clearance.

Target to be completed: will be completed as soon as after getting forest clearance.

  1. Installation of 2×5 MVA, 33/11 KV Sub-station at Mao with associated line

Status 

Sub-Station

  1. Erection of Equipment completed
  2. Control Room Building Completed
  3. Transformer Erection, panel erection in progress

Line

  1. Survey Completed
  2. Tower Erection – For 0.5 km out of 5.5 kms Completed

Target to be completed: June, 2017

  1. Installation of 2×5 MVA, 33/11 KV Sub-station at Mayangkhang with associated line

Status 

Sub-Station

  1. Land Development
  2. Foundation of Transformer, Major Equipment completed
  3. Control Room Building – brick work Completed
  4. Material and equipment supplied – 90%

Target to be completed: August, 2017

D) Transmission system (Under IPDS funding)

  1. Installation of 1×3.15 MVA 33KV S/S at Wangjing Moirangpalli

Status 

  1. Land Development is completed
  2. Gantry and Equipment foundation is in progress.
  3. Control room building- 60% completed
  4. Material and equipment supplied – 70%

Target to be completed: May, 2018

  1. Installation of 2×5 MVA 33KV S/S at Yairipok

Sub-Station

  1. Land Development is completed
  2. Transformer Foundation is completed
  3. Gantry and Equipment foundation is 90% completed.
  4. Control Room is completed.
  5. Material and equipment supplied – 70%

Target to be completed: May, 2018

  1. Installation of 2×5 MVA 33KV S/S at Heirok

Sub-Station

  1. Land Development is completed
  2. Transformer Foundation is completed
  3. Gantry and Equipment foundation is 90% completed.
  4. Control Room is completed.
  5. Material and equipment supplied – 70%

Target to be completed: May, 2018

  1. Installation of 2×5 MVA 33KV S/S at Wangoi

Sub-Station

  1. Site has been identified and land development to start shortly.
  2. Material and equipment supplied – 50%

Target to be completed: May, 2018

  1. Augmentation of 33/11 kV S/S from 1×3.15 MVA to 2×3.15 MVA at Kangpokpi

Sub-Station

  1. Material and equipment supplied – 50%

Target to be completed: May, 2018

  1. Augmentation of 33/11 kV S/S from 1×5 MVA to 2×5 MVA at Karong

Sub-Station

  1. Material and equipment supplied – 50%

Target to be completed: May, 2018