Click here to Download the Notice
Click here to Download the List of Eligible Candidates
Click here to Download the List of Rejected Candidates
All posts by MSPCL
Circular for Annual Perfomance Appraisal Forms (PAF) dated: 17th March 2022
Annexure -I (Manager) -Click here to download
Annexure -II (Deputy Manager)-Click here to download
Annexure-III(Assistant Manager)-Click here to download
Annexure-IV (Computer Operator)-Click here to download
Annexure-V (Control Room Assistant)-Click here to download
Annexure-VI(Junior System Assistant)-Click here to download
Annexure-VII(Watchman cum Cleaning Assistant)-Click here to download
Sl. No. | Particulars | Total Capacity (as on January, 2016) | Total Capacity (as on March, 2017) | Achievement during 2016-17 |
---|---|---|---|---|
1 | 132/33 KV transformation capacity | 517 MVA | 597 MVA | 80 MVA |
2 | 132 KV transmission lines | 537.1 Kms | 573.1Kms | 36 Kms |
3 | 33/11 KV transformation capacity | 508.2 MVA | 559.65 MVA | 51.45 MVA |
4 | 33 KV Sub-transmission lines | 1318.73 Kms | 1462.23 Kms | 143.5 Kms |
A) Transmission system (Under State Plan):
- Construction of 2×12.5 MVA 132 KV Substation along with associated 132 KV line & related works at Tipaimukh
Status
Sub-Station
- Foundation of Transformer, Gantry and Major Equipment completed
- Control Room Building is 95% Completed
Line
- Tower Erection is 50% completed.
- Stringing is yet to start.
Target to be completed: December, 2017
- Construction of 132 kV link transmission line for evacuation of power from 400/132 kV sub-station at Thoubal to 132 kV substations at Moreh
Status
- Work is in progress
Target to be completed: March, 2018
- Installation of 2×2.5MVA, 33/11 KV Sub-station at Kasom-Khullen with associated line
Status
Sub-Station
- Work Completed except Control room finishing, cable laying and termination
Line
- Pole Erection – 38 Km out of 41 Km completed
- Stringing – 36 Km out of 41 Km completed
Target to be completed: June, 2017
- Construction of 132 kV link transmission line for evacuation of power from 400/132 kV sub-station at Thoubal to 132 kV substations at Kongba, Yaingangpokpi and Hundung
Status
- Tower Foundation – 43 out of 44 nos completed
- Tower Erection – 34 out of 44 nos completed
- Stringing – 4.5 Km out of 11 Km completed
Target to be completed: June, 2017
- Construction of 33 kV D/C line on steel tubular poles from 132/33 kV sub-station, Thoubal to 33/11 kV sub-station at Thoubal (old)
Status
- Pole Erection is completed.
- Stringing – 5 Km out of 6 Km
Target to be completed: June, 2017
- Installation of 2×2.5 MVA 33KV S/S at Paoyi
Status
Work is in progress
Target to be completed: May, 2018
- Installation of 2×2.5 MVA 33KV S/S at Thuyeng
Status
Work is in progress
Target to be completed: May, 2018
- Installation of 2×2.5 MVA 33KV S/S at Gumnom
Status
Work is in progress
Target to be completed: May, 2018
- Upgradation of 33/11 kV Sub-Station at Khoupum by installing 2×2.5 MVA Transformer
Status
Work in progress- 20% completed
Target to be completed: February, 2018
- Installation of 2 nos. of 400kV Line bays at Imphal (PG) Sub-Station.
Status
15% of the work completed.
Target to be completed: March, 2018
- Installation of 132 kV S/C Line (2ndCkt) on D/C towers from Leimatak PH (NHPC) to 132 kV S/S at Ningthoukhong.
Status
35% of the work completed.
Target to be completed: November, 2017
- Construction of 132 kV S/C Line (3rdCkt) on D/C towers from 132 kV Yurembam S/S (State) to 132 kV Yurembam S/S (PGCIL)
Status
35% of the work completed.
Target to be completed: November, 2017
B) Transmission system (Under NLCPR funding & State Plan support)
- Construction of 3×105 MVA 400/132 KV Sub-Station at Thoubal
Status
- Completed and equipment testing in progress
Target to be completed: April, 2018
- Construction of 400KV line on D/C towers initially charged at 132 KV from Yurembam To Thoubal via Nambol
Status
- Tower Foundation – 116 towers completed out of 137.
- Tower Erection – 106 towers completed out of 137.
- Stringing – 20 Km out of 45.1 Km
Target to be completed: February, 2018
- Installation of 2×12.5 MVA, 132/33 KV S/S along with the associated 132 KV line & related civil works at Thanlon, Churachandpur District.
Status
Sub-Station
- Foundation of Transformer, Gantry and Major Equipment completed
- Control Room Building Completed
- 90% of the erection of major equipment completed.
Line
- Tower Foundation – 234 towers completed out of 242.
- Tower Erection – 224 towers completed out of 242.
- Stringing – 52.7 Km out of 66 Km
Target to be completed: September, 2017
- Installation of 2X12.5 MVA,132/33 KV Sub-station at Moreh with associated 132 KV line and related civil work on turn key basis under NLCPR
Status
Sub-Station
- Foundation of Transformer, Gantry and Major Equipment completed
- Control Room Building Completed
- Erection of major equipment is in progress.
Line
- Tower Foundation – 158 towers completed out of 181.
- Tower Erection – 70 towers completed out of 181.
- Stringing – 3 Km out of 45 Km
Target to be completed: September, 2017
- Installation of 2×5 MVA, 33/11 KV S/S along with the associated 33 KV line & related civil works at Nungbi Khullen, Ukhrul District.
Status
Sub-Station
- Foundation of Transformer, Gantry and Major Equipment completed
- Erection of gantry tower completed
- Control Room Building Completed
- Erection of major equipment is in progress.
Line
- Pole Erection – Completed
- Stringing – 42 Km out of 45 Km
Target to be completed: June, 2017
C) Transmission system (Under NEC funding & State Plan Support)
- Stringing of 132 KV S/C line Second Circuit on D/C Tower from Kakching to Churachandpur, Manipur
Status
- Work almost completed except two spans of 700 m due to forest clearance.
Target to be completed: will be completed as soon as after getting forest clearance.
- Installation of 2×5 MVA, 33/11 KV Sub-station at Mao with associated line
Status
Sub-Station
- Erection of Equipment completed
- Control Room Building Completed
- Transformer Erection, panel erection in progress
Line
- Survey Completed
- Tower Erection – For 0.5 km out of 5.5 kms Completed
Target to be completed: June, 2017
- Installation of 2×5 MVA, 33/11 KV Sub-station at Mayangkhang with associated line
Status
Sub-Station
- Land Development
- Foundation of Transformer, Major Equipment completed
- Control Room Building – brick work Completed
- Material and equipment supplied – 90%
Target to be completed: August, 2017
D) Transmission system (Under IPDS funding)
- Installation of 1×3.15 MVA 33KV S/S at Wangjing Moirangpalli
Status
- Land Development is completed
- Gantry and Equipment foundation is in progress.
- Control room building- 60% completed
- Material and equipment supplied – 70%
Target to be completed: May, 2018
- Installation of 2×5 MVA 33KV S/S at Yairipok
Sub-Station
- Land Development is completed
- Transformer Foundation is completed
- Gantry and Equipment foundation is 90% completed.
- Control Room is completed.
- Material and equipment supplied – 70%
Target to be completed: May, 2018
- Installation of 2×5 MVA 33KV S/S at Heirok
Sub-Station
- Land Development is completed
- Transformer Foundation is completed
- Gantry and Equipment foundation is 90% completed.
- Control Room is completed.
- Material and equipment supplied – 70%
Target to be completed: May, 2018
- Installation of 2×5 MVA 33KV S/S at Wangoi
Sub-Station
- Site has been identified and land development to start shortly.
- Material and equipment supplied – 50%
Target to be completed: May, 2018
- Augmentation of 33/11 kV S/S from 1×3.15 MVA to 2×3.15 MVA at Kangpokpi
Sub-Station
- Material and equipment supplied – 50%
Target to be completed: May, 2018
- Augmentation of 33/11 kV S/S from 1×5 MVA to 2×5 MVA at Karong
Sub-Station
- Material and equipment supplied – 50%
Target to be completed: May, 2018