Sl. No. | Particulars | Total Capacity (as on January, 2016) | Total Capacity (as on March, 2017) | Achievement during 2016-17 |
---|---|---|---|---|
1 | 132/33 KV transformation capacity | 517 MVA | 597 MVA | 80 MVA |
2 | 132 KV transmission lines | 537.1 Kms | 573.1Kms | 36 Kms |
3 | 33/11 KV transformation capacity | 508.2 MVA | 559.65 MVA | 51.45 MVA |
4 | 33 KV Sub-transmission lines | 1318.73 Kms | 1462.23 Kms | 143.5 Kms |